We have begun installing tanks, pumps, plumbing and soon electrical this week... this process of building the prototype, approving the vendor parts, and documenting the build to ensure manufacturing will be able to replicate consistently starting on boat #4 will continue throughout next week.
The hull liner was built today, it will be pulled and set in the boat next week and then the cabin build will begin.
Once we complete the under the deck work, and the initial cabin build, we're scheduled to set the deck onto the hull and bond together on April 21st. Right on schedule to have the first prototype to the water for testing and propping.
Next week it will start to look like a boat! Stay tuned for updates...